Timeline

Most recently we have updated the planning application to reflect local and stakeholder feedback. The next step is for the plans to be considered by Camden Council’s Planning committee. Below is a headline timeline outlining when we expect key activities and milestones to happen. 

Early 2021:

Pre-submission public consultation on early proposals

Summer 2021:

Submission of planning application for original scheme by previous owner LabTech

March/April 2022:

Amendments proposed to the scheme, and a second public consultation took place (including an in-person exhibition and site tours)

June 2022:

BC Partners acquire the site from LabTech

August/September 2022:

Further engagement with stakeholders and community groups regarding the revised proposals

September 2022:

Amendments to the planning application are submitted to Camden Council

June 2023:

Amended planning application submitted, following the listing of two buildings at West Central Street

Q3/Q4 2023:

Camden Council Planning Committee decision expected

2024 - 2028:

Demolition, enabling and main construction works (Subject to planning permission) 

We aim to continue to work with the local community and grow our local relationships as the development progresses. We are keen to continue to meet with local groups and organisations to share the plans and discuss ideas for getting involved. Please don’t hesitate to get in touch with the team to if you’d like to discuss this further or have any questions.  